1
00:00:17,920 --> 00:00:21,070
Kyle Jacob Austin here,
owner of Q zone.
2
00:00:21,070 --> 00:00:26,140
And welcome to episode 25 of The
Subcontractors Blueprint, the show
3
00:00:26,140 --> 00:00:30,070
where subcontractors will learn how
to ensure profitability, improve
4
00:00:30,070 --> 00:00:35,080
cashflow and grow their business.
Today's episode, number 25 is
5
00:00:35,080 --> 00:00:38,830
going to be about defects.
And this is another one of those
6
00:00:38,830 --> 00:00:42,940
things where in construction we
don't have a proper definition
7
00:00:42,940 --> 00:00:46,540
of the word defect.
The NHC contract has a definition
8
00:00:46,540 --> 00:00:49,870
which says something like a part
of the works, which is not in
9
00:00:49,870 --> 00:00:54,310
accordance with the scope or part of
the designed work, which is not in
10
00:00:54,310 --> 00:00:59,410
accordance with either applicable
law or the accepted design, whereas
11
00:00:59,410 --> 00:01:03,790
the JCT is completely silent on it,
and all it says somewhere is that the
12
00:01:03,790 --> 00:01:08,830
contractor must go and make good
defects, shrinkage or other faults.
13
00:01:08,830 --> 00:01:12,850
Some people take a fairly
simplistic definition of the word,
14
00:01:12,850 --> 00:01:16,120
and take it to mean something
that doesn't do what it should,
15
00:01:16,120 --> 00:01:19,840
or perform how it should.
And I would say in broader terms
16
00:01:19,840 --> 00:01:24,370
that it is work that doesn't meet
either the specification or the
17
00:01:24,370 --> 00:01:28,600
standard that was required by the
contract due to faults in the work,
18
00:01:28,600 --> 00:01:32,950
faults in the materials or design,
and deficiencies in quality.
19
00:01:32,950 --> 00:01:36,370
And there are two types of defects
that get spoken about in the
20
00:01:36,370 --> 00:01:41,920
construction industry, which are
latent defects and patent defects.
21
00:01:41,920 --> 00:01:44,890
So let's first talk about what
the difference is between those
22
00:01:44,890 --> 00:01:47,620
two things.
So patent in this sense is
23
00:01:47,620 --> 00:01:52,540
meaning easily recognizable
obvious think patently clear.
24
00:01:52,540 --> 00:01:55,990
You don't have to go looking for it.
It just is not right.
25
00:01:55,990 --> 00:01:59,860
So let's discuss an example on that.
And we'll use the same example
26
00:01:59,860 --> 00:02:04,180
in latent and patent defect form
of a crack on a wall.
27
00:02:04,180 --> 00:02:08,560
So I had a patent defect on a
project we were constructing.
28
00:02:08,560 --> 00:02:12,910
The external wall is supported by
a steel frame and one section of
29
00:02:12,910 --> 00:02:16,750
the building cantilevered out so
that you could walk underneath it.
30
00:02:16,750 --> 00:02:20,620
And it was actually designed like
that, so that cars that were exiting
31
00:02:20,620 --> 00:02:24,550
the car park of the building didn't
have a corner of the building in
32
00:02:24,550 --> 00:02:27,250
their way, as they're looking
around to make sure there's no
33
00:02:27,250 --> 00:02:31,120
pedestrians or vehicles coming.
But that corner had another five
34
00:02:31,120 --> 00:02:35,380
stories of building above it.
And as the masonry continued to be
35
00:02:35,380 --> 00:02:39,190
built all the way up to the top
course, the extra weight and the
36
00:02:39,190 --> 00:02:43,000
load on that corner was causing
some deflection in the steel,
37
00:02:43,000 --> 00:02:47,980
and a crack appeared at the junction
between the last vertical column that
38
00:02:47,980 --> 00:02:51,280
went all the way down to the ground,
and the large steel which was
39
00:02:51,280 --> 00:02:54,670
projecting horizontally,
which was then carrying the five
40
00:02:54,670 --> 00:02:58,330
stories of building above it.
And we had the clients car of
41
00:02:58,330 --> 00:03:00,970
works coming around,
taking great delight in telling
42
00:03:00,970 --> 00:03:03,010
us that we've got a problem.
Oh no,
43
00:03:03,010 --> 00:03:06,790
the building is going to fall down.
And whilst no such thing actually did
44
00:03:06,790 --> 00:03:10,960
happen, it was cause for concern.
And what you could see was this
45
00:03:10,960 --> 00:03:14,590
large crack appearing at the
junction between the connection.
46
00:03:14,590 --> 00:03:18,340
The lintel that was there, taking
the load was all still in place.
47
00:03:18,340 --> 00:03:21,280
No problems with that,
but there was this crack that
48
00:03:21,280 --> 00:03:23,980
had gone straight through the
bricks in a pretty much straight
49
00:03:23,980 --> 00:03:27,790
line through about ten courses,
and that was a patent defect.
50
00:03:27,790 --> 00:03:30,160
You could clearly see it.
There was no need to break any
51
00:03:30,160 --> 00:03:32,800
surface finishing to expose the
defect.
52
00:03:32,800 --> 00:03:37,450
It was there in plain sight, obvious,
clear as day and what we had to do.
53
00:03:37,480 --> 00:03:39,370
We invited the structural
engineer out.
54
00:03:39,370 --> 00:03:43,000
We broke away the brickwork where the
cracks had formed and exposed the
55
00:03:43,000 --> 00:03:47,200
steel connection, and we just let it
stand for a matter of a few weeks.
56
00:03:47,200 --> 00:03:50,590
The structural engineer was satisfied
when he had his second visit that
57
00:03:50,590 --> 00:03:54,460
there was nothing happening to that
joint, and all it was was a defect
58
00:03:54,460 --> 00:03:58,630
that was caused by the weight of
the masonry above loading down and
59
00:03:58,630 --> 00:04:02,110
bearing down on the supporting steel.
Now that happened whilst we were
60
00:04:02,110 --> 00:04:04,210
on site,
you could say that we're actually
61
00:04:04,210 --> 00:04:07,750
lucky that we were still there.
We still had scaffolds on site,
62
00:04:07,750 --> 00:04:10,480
we still had bricklayers there
doing something else.
63
00:04:10,480 --> 00:04:14,650
So we had all of the means to
correct the defect at our disposal.
64
00:04:14,650 --> 00:04:18,160
And that is where latent defects
become a bit more of an issue,
65
00:04:18,160 --> 00:04:21,580
because once the building is handed
over, retentions are released,
66
00:04:21,580 --> 00:04:24,820
everybody's contracts are finished.
Your site team moves on to
67
00:04:24,820 --> 00:04:27,880
something completely different.
It becomes an altogether bigger
68
00:04:27,880 --> 00:04:31,510
problem to start investigating it
in the first part and then putting
69
00:04:31,510 --> 00:04:35,110
it right. So a latent defect.
Then let's look at the same defect
70
00:04:35,110 --> 00:04:39,160
and pretend that was a latent defect.
If we'd have handed that building
71
00:04:39,160 --> 00:04:42,700
over and there hadn't been that
problem, that natural settlement,
72
00:04:42,700 --> 00:04:47,020
that deflection has yet to really
occur, then perhaps 6 or 8 years
73
00:04:47,020 --> 00:04:51,130
down the line, a new occupier of
the building decides to bring his
74
00:04:51,130 --> 00:04:55,570
book collection to his new office
and lines the room with a small
75
00:04:55,570 --> 00:04:59,980
library of biology textbooks and
his 20 years of research.
76
00:04:59,980 --> 00:05:03,010
And this creates this massive
load that wasn't there before.
77
00:05:03,010 --> 00:05:05,620
All of a sudden,
the building is deflecting and
78
00:05:05,620 --> 00:05:08,950
this crack appears all right.
A lot of weight has been added.
79
00:05:08,950 --> 00:05:12,400
But let's say that that's within the
performance parameters of the floor.
80
00:05:12,400 --> 00:05:15,580
So the contractor now has to re
mobilize the site, bring his
81
00:05:15,580 --> 00:05:19,640
structural engineer, pay his.
Tried to provide the access to
82
00:05:19,640 --> 00:05:23,210
break open the wall,
exposing that steel connection.
83
00:05:23,210 --> 00:05:27,260
And this time, let's say one of the
bolts is sheared off and it must
84
00:05:27,260 --> 00:05:30,800
have had a manufacturing defect.
But that defect got built in.
85
00:05:30,800 --> 00:05:35,150
It wasn't clear and obvious.
It didn't manifest until years later.
86
00:05:35,150 --> 00:05:38,720
You couldn't have possibly known
about it and corrected for it whilst
87
00:05:38,720 --> 00:05:43,280
the construction was still happening,
and thereby a reasonable inspection
88
00:05:43,280 --> 00:05:47,030
that had taken place at handover
could never have spotted that.
89
00:05:47,030 --> 00:05:51,530
And it's a hidden or dormant problem.
There's often not a lot that the
90
00:05:51,530 --> 00:05:55,310
client can do about a latent defect.
They obviously have that contractual
91
00:05:55,310 --> 00:05:59,240
link back to the contractor,
and perhaps if the contractor is
92
00:05:59,240 --> 00:06:03,830
gone insolvent, they've asked for
collateral warranty, which provides
93
00:06:03,830 --> 00:06:08,570
a third party link back to, say,
the designing steelwork contractor,
94
00:06:08,570 --> 00:06:11,930
the structural engineer,
the architect involved in the scheme.
95
00:06:12,140 --> 00:06:16,100
By a period of years later,
any retention has been held on.
96
00:06:16,100 --> 00:06:19,850
The project has long since been
paid out and unless there is a
97
00:06:19,850 --> 00:06:23,150
latent defect insurance,
which there often is in the case of,
98
00:06:23,180 --> 00:06:27,500
say, housing projects,
your premier guarantee, or NBC,
99
00:06:27,500 --> 00:06:30,950
those types of cover there
exactly that they are there to
100
00:06:30,950 --> 00:06:34,550
provide for latent defects,
common types and causes of latent
101
00:06:34,550 --> 00:06:38,870
defects, and most often out of
design and manufacturing faults.
102
00:06:38,870 --> 00:06:43,400
Issues with the structure that are
hidden behind plasterboard finishes,
103
00:06:43,400 --> 00:06:47,120
leaking plumbing joints,
small perforations in a roof
104
00:06:47,120 --> 00:06:50,870
that then get bigger over time,
faulty electric systems,
105
00:06:50,870 --> 00:06:54,440
ventilation that doesn't perform
as it's designed, which might
106
00:06:54,440 --> 00:06:58,670
then lead to damp problems.
Drainage that isn't sufficient
107
00:06:58,670 --> 00:07:01,820
when you get to heavy rain,
whether as a subcontractor.
108
00:07:01,820 --> 00:07:05,090
These might sound like things
that you can't do anything about,
109
00:07:05,090 --> 00:07:07,700
but there are some factors that
can contribute.
110
00:07:07,730 --> 00:07:12,620
You've got poor workmanship, either
by using poorly qualified staff or
111
00:07:12,620 --> 00:07:16,040
staff that are on too keen a price,
so they're cutting corners and
112
00:07:16,040 --> 00:07:20,870
leaving things not properly finished.
You've got poor quality products and
113
00:07:20,870 --> 00:07:24,320
you've got potentially poor design,
and the limited things that you
114
00:07:24,320 --> 00:07:28,310
can do to prevent these kind of
issues is just making sure that
115
00:07:28,310 --> 00:07:31,520
you're buying quality products.
You're checking that your staff
116
00:07:31,520 --> 00:07:34,040
that you're employing are
suitably qualified.
117
00:07:34,040 --> 00:07:37,340
And if you are responsible for
design, that you're using a
118
00:07:37,340 --> 00:07:41,870
responsible and reputable designer.
If you are called back to some kind
119
00:07:41,870 --> 00:07:45,800
of investigation, then you might
be presented with reports such as
120
00:07:45,800 --> 00:07:50,390
moisture assessments or thermal
imaging, photographs and videos
121
00:07:50,390 --> 00:07:54,350
or photos taken via a bore scope.
Or even these might be things
122
00:07:54,350 --> 00:07:58,580
that you think are sensible to
do to investigate a defect,
123
00:07:58,580 --> 00:08:02,180
and you might be called in at
the sign of an uneven floor,
124
00:08:02,210 --> 00:08:07,100
the presence of moisture or mold
or cracks in walls and ceilings.
125
00:08:07,100 --> 00:08:09,680
Any one of these things can
present itself.
126
00:08:09,680 --> 00:08:13,610
And then it's a reason to probe
further and try and seek out
127
00:08:13,610 --> 00:08:16,610
what the problem is.
Now, if you get called back to look
128
00:08:16,610 --> 00:08:20,600
at a defect, the best thing that
you can do is to crack on with it.
129
00:08:20,600 --> 00:08:24,680
Acting quickly is an essential
preventative measure.
130
00:08:24,680 --> 00:08:27,890
You won't see this as a problem
that you nip in the bud before it
131
00:08:27,890 --> 00:08:32,090
turns into a much larger issue,
and as well as doing the obvious in
132
00:08:32,090 --> 00:08:36,770
repairing damaged furnishings and
repairing and reinforcing pieces that
133
00:08:36,770 --> 00:08:39,650
have broken, you want to consider
whether what you're doing is going
134
00:08:39,650 --> 00:08:42,800
to fix the problem long term,
and that might mean throwing
135
00:08:42,800 --> 00:08:45,230
some money at the problem.
But on the flip side of that,
136
00:08:45,230 --> 00:08:48,770
if it prevents it from turning
into a larger problem or prevents
137
00:08:48,770 --> 00:08:51,860
it from reoccurring and you
revisiting and putting it right
138
00:08:51,860 --> 00:08:55,520
again in the future, then that is
potentially the best thing to do.
139
00:08:55,520 --> 00:08:59,060
And what you don't want is something
that is now a small issue,
140
00:08:59,060 --> 00:09:01,850
developing and turning into
something much larger,
141
00:09:01,850 --> 00:09:05,540
and also growing into a health and
safety problem and potentially
142
00:09:05,540 --> 00:09:08,990
injuring somebody down the line.
And a further point on this,
143
00:09:08,990 --> 00:09:12,200
it's much better for you to get
involved in rectify the issue
144
00:09:12,200 --> 00:09:15,800
than let the employer refer the
matter to their insurer.
145
00:09:15,830 --> 00:09:19,490
Their insurer will probably
correct the issue themselves.
146
00:09:19,490 --> 00:09:22,910
They won't use a particularly
competitive contractor to put
147
00:09:22,910 --> 00:09:25,160
the work right.
They will use somebody that they
148
00:09:25,160 --> 00:09:28,550
know and trust, probably on some
kind of schedule of rates,
149
00:09:28,550 --> 00:09:32,420
that they can quickly mobilize and
get on site to sort the problem out,
150
00:09:32,420 --> 00:09:36,140
and then they'll add to that all
of their administration fees and
151
00:09:36,140 --> 00:09:38,990
whatever payout they agree with
the building user.
152
00:09:38,990 --> 00:09:42,410
And much of that might be
avoided by some proactive effort
153
00:09:42,410 --> 00:09:46,340
on your part to get back to site
and sort the issue out yourself.
154
00:09:46,730 --> 00:09:50,210
Now, going back to patent defects,
these can be defects that are
155
00:09:50,210 --> 00:09:53,090
clear and obvious, either during
the construction of the building
156
00:09:53,090 --> 00:09:56,780
itself or that crop up within
the defects liability period.
157
00:09:56,780 --> 00:10:00,080
And the whole point of that period
is that it's reasonably common for
158
00:10:00,080 --> 00:10:04,070
the majority of issues within a
building to rear their heads within
159
00:10:04,070 --> 00:10:07,550
the first year of it being finished,
and defects that are found during
160
00:10:07,550 --> 00:10:11,480
the defects liability period are
dealt with largely the same as
161
00:10:11,480 --> 00:10:13,640
we've just discussed.
For latent defects,
162
00:10:13,640 --> 00:10:17,000
the best thing that you can do
is be proactive about attending.
163
00:10:17,270 --> 00:10:21,230
Sight identifying what the problem
is discussing with the contractor,
164
00:10:21,230 --> 00:10:24,260
whether it's your fault or whether
it's the fault of some materials
165
00:10:24,260 --> 00:10:27,560
that somebody else's provided,
or it's somebody else's work
166
00:10:27,560 --> 00:10:30,170
that's caused the problem.
All of these things are best off
167
00:10:30,170 --> 00:10:33,320
done up front, and then the
sooner that is rectified,
168
00:10:33,320 --> 00:10:37,130
the better it is for everybody.
During the course of the job.
169
00:10:37,130 --> 00:10:40,700
It's a bit of a different situation.
You obviously have got your lads
170
00:10:40,700 --> 00:10:44,060
there, you've got materials,
the site managers there to see
171
00:10:44,060 --> 00:10:46,970
things and to check on the
quality of this and that.
172
00:10:46,970 --> 00:10:49,820
And at various points you might
be pulled up and asked to correct
173
00:10:49,820 --> 00:10:53,360
something in the majority of cases
because you know what you're doing,
174
00:10:53,360 --> 00:10:55,460
you're constructing to design
drawings.
175
00:10:55,460 --> 00:10:58,820
Usually these are little bits of
workmanship or something that didn't
176
00:10:58,820 --> 00:11:01,970
quite get finished on one shift.
Somebody come in the following day
177
00:11:01,970 --> 00:11:05,000
and started on something else and
left a little bit of work behind.
178
00:11:05,000 --> 00:11:07,760
And those little bits of odds
and ends that need to be picked
179
00:11:07,760 --> 00:11:10,340
up and completed.
Quite often these things can
180
00:11:10,340 --> 00:11:13,250
seem insignificant.
But from the contractor's point of
181
00:11:13,250 --> 00:11:16,490
view, there's often an issue where
you can't then get the follow on
182
00:11:16,490 --> 00:11:20,480
trade to start because he hasn't got
a full run at the work until you
183
00:11:20,480 --> 00:11:24,530
fully finished all of your work and
these little bits of small scale
184
00:11:24,530 --> 00:11:29,030
issues, minute defects, this is what
your attention is really there for,
185
00:11:29,060 --> 00:11:32,420
is to keep some skin in the game for
each of the supply chain, to make
186
00:11:32,420 --> 00:11:35,990
sure they come back and do the right
thing and finish off their work.
187
00:11:35,990 --> 00:11:39,080
But you occasionally get something
really quite significant.
188
00:11:39,080 --> 00:11:42,680
Let's say there's a retaining wall,
and rather than following the design
189
00:11:42,680 --> 00:11:47,000
details for it, which showed an
English bund brickwork wall out
190
00:11:47,000 --> 00:11:50,390
of class B engineering bricks,
the contractor has gone rogue and
191
00:11:50,390 --> 00:11:54,110
built one skin out of seven and
a half Newton block work and one
192
00:11:54,110 --> 00:11:57,680
skin out of engineering bricks.
And once the wall is finished
193
00:11:57,680 --> 00:12:00,380
and they've backfilled behind
the block work, you probably
194
00:12:00,380 --> 00:12:03,410
wouldn't know anything was wrong.
But the issue with that is when
195
00:12:03,410 --> 00:12:06,140
you're building out of English bond,
the two skins of brickwork are
196
00:12:06,140 --> 00:12:10,130
naturally tied together by the bond,
and also a seven and a half Newton
197
00:12:10,130 --> 00:12:14,330
block is one tenth of the strength
of a class B engineering brick.
198
00:12:14,330 --> 00:12:17,750
So a couple together, you've got a
far, far weaker structure and it's
199
00:12:17,750 --> 00:12:21,560
not likely to perform to the same
standards as the original design.
200
00:12:21,560 --> 00:12:24,800
Now, in spite of that work being
finished, it's a clear defect.
201
00:12:24,800 --> 00:12:27,440
It falls short of the standard
required by the contract,
202
00:12:27,440 --> 00:12:31,010
and the finished wall is of
lesser specification than what
203
00:12:31,010 --> 00:12:33,710
has been bought.
So in this instance, the contractor
204
00:12:33,710 --> 00:12:37,640
is able to make an adjustment pending
that piece of work being put right.
205
00:12:37,640 --> 00:12:40,700
And that adjustment is likely
going to be more than the cost of
206
00:12:40,700 --> 00:12:43,190
building the wall in the first place,
because they're now in a
207
00:12:43,190 --> 00:12:46,520
situation where not only have
they got to build the wall again,
208
00:12:46,520 --> 00:12:49,580
they've got to demolish what's
there and dispose of it all.
209
00:12:49,580 --> 00:12:52,460
So a word of warning if you're
thinking of deviating from the
210
00:12:52,460 --> 00:12:55,190
specification,
because when that comes back to bite,
211
00:12:55,190 --> 00:12:58,370
it will hurt and you'll be
expected to put it right now in
212
00:12:58,370 --> 00:13:02,330
a slightly different situation.
Let's say there's been a cavity wall
213
00:13:02,330 --> 00:13:05,720
constructed, and for some reason,
the clerk of work suspects that
214
00:13:05,720 --> 00:13:09,650
the fire barriers have not been
fully fitted in all places shown
215
00:13:09,650 --> 00:13:12,800
on the fire strategy drawing.
Now, what the Clerk of Works can
216
00:13:12,800 --> 00:13:16,220
do and what will happen is the
contractor will issue the same
217
00:13:16,220 --> 00:13:20,480
instruction downstream to you as
they can issue a direction or an
218
00:13:20,480 --> 00:13:24,080
instruction to open up the work.
And what the proviso is in this
219
00:13:24,080 --> 00:13:27,620
instance is that the clock of
work isn't fully certain that
220
00:13:27,620 --> 00:13:30,440
there is a defect.
So this instruction to open up the
221
00:13:30,440 --> 00:13:33,740
works is a test to check whether
you're meeting the specification
222
00:13:33,740 --> 00:13:37,730
or not, and whoever is found to
be wrong in this situation is
223
00:13:37,730 --> 00:13:41,180
the person who bears the cost.
So for this particular example,
224
00:13:41,180 --> 00:13:44,600
we're going to have to break into the
facing brickwork and expose some
225
00:13:44,600 --> 00:13:48,980
areas where we would expect there
to be a cavity barrier installed.
226
00:13:48,980 --> 00:13:52,460
Take a photographic record to
demonstrate whether it's there or
227
00:13:52,460 --> 00:13:56,750
not, and close up the work again,
reinstating the facing brickwork.
228
00:13:56,750 --> 00:14:00,110
Now, if the clock of works is wrong
and the proved to not be a defect,
229
00:14:00,110 --> 00:14:03,080
then the cost of that testing
can be added to the final
230
00:14:03,080 --> 00:14:06,380
account as a variation.
Now, under a JCT contract,
231
00:14:06,380 --> 00:14:09,740
there's no obligation for these
kind of defects to be notified
232
00:14:09,740 --> 00:14:12,980
at any particular time,
and sometimes it can seem like the
233
00:14:12,980 --> 00:14:16,790
clerk of works will store up these
issues and then drop them all out
234
00:14:16,790 --> 00:14:19,820
at a critical point in the job.
And this position does seem a
235
00:14:19,820 --> 00:14:23,330
little bit unfair, because the
contractor is obliged to notify
236
00:14:23,330 --> 00:14:26,450
issues once they've occurred,
and even more proactively under
237
00:14:26,450 --> 00:14:29,990
the NEC form of contract, they're
required to give an early warning
238
00:14:29,990 --> 00:14:35,030
notice if they foresee that anything
could affect time, cost or quality.
239
00:14:35,030 --> 00:14:38,510
So why shouldn't the same apply
to the employer and their clerk
240
00:14:38,510 --> 00:14:42,410
of works or supervisor?
Finally, then there is a possibility
241
00:14:42,410 --> 00:14:46,190
of damages being awarded or
becoming liable for damages as a
242
00:14:46,190 --> 00:14:49,490
result of there being a defect.
And firstly with this,
243
00:14:49,490 --> 00:14:53,840
damages can only be deducted from
you as a subcontractor if the same
244
00:14:53,840 --> 00:14:57,770
damages have been deducted from
the contractor by their client,
245
00:14:57,770 --> 00:15:01,940
or alternatively, if there are some
costs incurred by the contractor
246
00:15:01,940 --> 00:15:05,690
as a result of your defect that
are perhaps incurred by another
247
00:15:05,690 --> 00:15:10,130
contractor, there would be able to
contra charge you for that cost.
248
00:15:10,130 --> 00:15:13,430
However, on occasion the client
may decide that okay,
249
00:15:13,430 --> 00:15:16,880
this defect has happened.
Whilst we go back to that, we don't
250
00:15:16,880 --> 00:15:20,420
just want to put the defect right,
we want to improve the situation.
251
00:15:20,420 --> 00:15:22,520
Let's say there's been a fault
with the roofing.
252
00:15:22,520 --> 00:15:25,550
The flat roof membrane gets
ripped out and replaced,
253
00:15:25,550 --> 00:15:28,640
but the employer decides that
they also want to operate the
254
00:15:28,640 --> 00:15:31,910
insulation whilst they're there.
The principle is that where
255
00:15:31,910 --> 00:15:35,270
corrective action is taken, it
should put the employer back in the.
256
00:15:35,380 --> 00:15:38,800
Position that they started in,
i.e. as if there hadn't been a
257
00:15:38,800 --> 00:15:41,500
defect in the first place.
So in that instance,
258
00:15:41,500 --> 00:15:45,190
the employer should be paying for
that increased spec of insulation
259
00:15:45,190 --> 00:15:48,370
and they should be contributing
towards your cost of being there.
260
00:15:48,670 --> 00:15:50,320
I hope you've enjoyed today's
episode.
261
00:15:50,350 --> 00:15:54,070
My mission is to help the
million SME subcontractors
262
00:15:54,070 --> 00:15:57,190
working within our industry.
If you've taken some value away
263
00:15:57,190 --> 00:16:00,250
from today's episode,
I'd love it if you share the show and
264
00:16:00,250 --> 00:16:03,820
pass that value on to somebody else
who would benefit from hearing it.
265
00:16:03,820 --> 00:16:06,430
And thanks for tuning in.
If you like what you've heard
266
00:16:06,430 --> 00:16:11,530
and you want to learn more,
please do find us at WCW's zone.
267
00:16:11,530 --> 00:16:17,080
That's the letters QRS dot zone zone,
where you can subscribe to our
268
00:16:17,080 --> 00:16:20,170
training and support system for
like minded subcontractors.
269
00:16:20,170 --> 00:16:24,040
In there you'll find templates,
how to videos, interviews, and more.
270
00:16:24,070 --> 00:16:26,470
It's less than the price of a
cup of coffee per day,
271
00:16:26,470 --> 00:16:30,130
and you can cancel any time or
also on all of your favourite
272
00:16:30,130 --> 00:16:35,140
socials at Qe7. Thanks again!
I've been Jacob Austin and
273
00:16:35,140 --> 00:16:36,040
you've been awesome!