1
00:00:17,190 --> 00:00:19,080
Hi everyone.
Jacob Austin here,
2
00:00:19,080 --> 00:00:23,760
owner of Quest Zone.
And welcome to episode 24 of The
3
00:00:23,760 --> 00:00:28,080
Subcontractors Blueprint, the show
where subcontractors will learn how
4
00:00:28,080 --> 00:00:32,640
to ensure profitability, improve
cashflow and grow their business.
5
00:00:33,460 --> 00:00:38,410
So I'm doing episode 24 today.
It's the first show of the new year
6
00:00:38,410 --> 00:00:45,850
in 2024, 24 in 2024. Sounds good.
Today's episode is going to be
7
00:00:45,850 --> 00:00:51,430
about design and build
subcontracts and design liability.
8
00:00:51,460 --> 00:00:54,490
There are several different ways
that you could be appointed to
9
00:00:54,490 --> 00:00:58,450
carry out design on a typical
project for our main contractor.
10
00:00:58,660 --> 00:01:01,780
So you have the standard
building subcontract with
11
00:01:01,780 --> 00:01:06,310
subcontractors design.
You have a design and build
12
00:01:06,310 --> 00:01:10,900
subcontract, you have a minor
work subcontract with design.
13
00:01:10,900 --> 00:01:16,390
And then there's the neck form.
Any of the neck options can be
14
00:01:16,390 --> 00:01:20,590
used with subcontract design.
It's a little bit more fluid.
15
00:01:20,620 --> 00:01:24,610
They give you the option to add
in certain requirements and
16
00:01:24,610 --> 00:01:28,420
stipulations wherever you want,
and it's more customizable.
17
00:01:28,420 --> 00:01:31,870
I think the neck form of contract.
So it is straightforward to
18
00:01:31,870 --> 00:01:35,950
introduce that subcontract
design into any subcontract,
19
00:01:35,950 --> 00:01:41,050
as it's the most common subcontract.
I'm going to refer to the JCT design
20
00:01:41,050 --> 00:01:46,540
and build subcontract, and we'll use
that as the lens for today's episode.
21
00:01:46,780 --> 00:01:52,510
I start with subcontract design.
So design liability, any design that
22
00:01:52,510 --> 00:01:57,040
you produce as a subcontractor,
you'll be liable for any errors.
23
00:01:57,040 --> 00:02:01,000
You'll be liable for faults that
occur as a result of your design.
24
00:02:01,000 --> 00:02:07,180
So you are obliged under the
subcontract and via tort law,
25
00:02:07,180 --> 00:02:11,020
to make sure that your design is
correct, to make sure that it is
26
00:02:11,020 --> 00:02:14,710
designed properly with skill and
proper skill and care.
27
00:02:14,710 --> 00:02:19,840
One thing to be careful of is that
where the design is stipulated,
28
00:02:19,840 --> 00:02:23,980
where the requirements are laid out,
there is no requirement for you
29
00:02:23,980 --> 00:02:30,190
to design a fit for purpose item.
So let's say you're encumbered
30
00:02:30,190 --> 00:02:34,570
with designing the concrete floor,
the precast concrete floor for a
31
00:02:34,570 --> 00:02:37,480
steel frame project.
Somewhere along the line there's
32
00:02:37,480 --> 00:02:41,500
a fitness for purpose statement
within the requirements.
33
00:02:41,500 --> 00:02:44,680
So within the requirements there's
a fitness for purpose statement.
34
00:02:44,680 --> 00:02:50,500
Now, the problem with fitness for
purpose is that it's a really woolly
35
00:02:50,500 --> 00:02:56,410
phrase, and it brings in all manner
of risk and all manner of issues.
36
00:02:56,410 --> 00:03:01,330
So by the courts, the courts have
used and abused this phrase and
37
00:03:01,330 --> 00:03:04,810
used it to incorporate all kinds
of requirements which aren't
38
00:03:04,810 --> 00:03:09,040
necessarily expressly written out.
And the issue with it is that
39
00:03:09,040 --> 00:03:13,210
sometimes the employer will use the
building for a particular purpose,
40
00:03:13,210 --> 00:03:18,640
but within his requirements he will
state, I want a floor that can do x.
41
00:03:18,640 --> 00:03:23,110
I want you to design me a floor that
fits in this space and it needs
42
00:03:23,110 --> 00:03:26,980
to carry this amount of weight.
So you design to those criteria.
43
00:03:26,980 --> 00:03:30,310
But then the fitness for purpose
element may take it above and
44
00:03:30,310 --> 00:03:33,640
beyond that.
So okay they've said I want it
45
00:03:33,640 --> 00:03:37,030
to cater to this weight.
But well let's just say that
46
00:03:37,030 --> 00:03:42,310
that precast floor is actually
in a large leisure facility.
47
00:03:42,310 --> 00:03:45,040
And part of the leisure facility
is a gym.
48
00:03:45,040 --> 00:03:48,190
So within that gym they're going
to be lifting weights.
49
00:03:48,190 --> 00:03:51,940
And they're not just lightweights.
We're talking deadlifts,
50
00:03:51,940 --> 00:03:56,440
several hundred kilograms worth
of deadlifts and weights,
51
00:03:56,530 --> 00:04:01,060
perhaps going to be lifted up and
dropped freehand onto the floor.
52
00:04:01,060 --> 00:04:05,680
And regardless of whether somebody
has stated that within the employer's
53
00:04:05,680 --> 00:04:09,010
requirements that whether they've
told you those are going to be the
54
00:04:09,010 --> 00:04:12,460
conditions that that floor is going
to be used under, you are going to
55
00:04:12,460 --> 00:04:16,150
be expected to know that that is
what the building is being used for.
56
00:04:16,180 --> 00:04:19,810
Why haven't you designed a floor
that can withstand those kind of
57
00:04:19,810 --> 00:04:23,170
pressures?
So it introduces the possibility
58
00:04:23,170 --> 00:04:26,350
of requirements beyond what is
being specified.
59
00:04:26,350 --> 00:04:28,870
And that's the issue with
fitness for purpose.
60
00:04:28,870 --> 00:04:34,540
So why is that important to you.
So as a subcontractor you will have
61
00:04:34,540 --> 00:04:38,800
a professional indemnity policy.
If you are a designing subcontractor,
62
00:04:38,800 --> 00:04:43,270
if you're subletting your design,
your sub designer will have a
63
00:04:43,270 --> 00:04:47,740
professional indemnity policy.
And the issue is that professional
64
00:04:47,740 --> 00:04:52,000
indemnity insurance only covers
you for professional negligence.
65
00:04:52,000 --> 00:04:56,620
So this is a failure for you to
exercise the reasonable skill
66
00:04:56,620 --> 00:04:59,920
and care that you might do in
carrying out a design.
67
00:04:59,920 --> 00:05:04,330
So because fitness for purpose
includes these additional
68
00:05:04,330 --> 00:05:07,990
requirements that may not be stated,
what you're actually doing is
69
00:05:07,990 --> 00:05:12,520
exposing yourself to any risk
beyond the level of reasonable
70
00:05:12,520 --> 00:05:15,610
skill and care, up to the level
of fitness for purpose.
71
00:05:15,610 --> 00:05:19,480
So you might be uninsured and
that might cost you a fortune.
72
00:05:19,480 --> 00:05:23,500
We're talking if we're having to
rip out and replace floors.
73
00:05:23,500 --> 00:05:28,450
Going back to the same example in a
live building, the person using the
74
00:05:28,450 --> 00:05:34,150
building has lost their use of it.
You are liable for all of that.
75
00:05:34,330 --> 00:05:40,180
Moving the tenant out, moving them
into temporary accommodation,
76
00:05:40,180 --> 00:05:43,000
maybe setting them straight for loss
of income. That. I have incurred.
77
00:05:43,000 --> 00:05:46,240
Whilst I have not been able to use
the building and also refunding
78
00:05:46,240 --> 00:05:50,140
their customers who say subscription
they haven't been able to use,
79
00:05:50,140 --> 00:05:53,320
and they might even argue because
this is a leisure facility,
80
00:05:53,320 --> 00:05:55,930
that some of their customers
have now gone elsewhere,
81
00:05:55,930 --> 00:05:59,440
they've set up their membership with
a different facility, and they've
82
00:05:59,440 --> 00:06:02,230
lost ongoing forward revenue.
And that's a level of difference.
83
00:06:02,230 --> 00:06:05,620
We're talking between fitness for
purpose and just designing with
84
00:06:05,620 --> 00:06:09,460
the reasonable skill and care that
would be expected of a professional.
85
00:06:09,460 --> 00:06:14,050
And this is why it matters so much,
because the issue is that this duty
86
00:06:14,050 --> 00:06:18,280
to design to fitness for purpose
goes beyond professional negligence,
87
00:06:18,280 --> 00:06:21,310
and it's an absolute requirement
that you've got to satisfy.
88
00:06:21,370 --> 00:06:27,370
So this makes it a greater demand.
And rather than just being liable for
89
00:06:27,370 --> 00:06:31,150
negligence, and you would have to
be proved to be negligent in the
90
00:06:31,150 --> 00:06:35,260
case of a regular design liability,
the requirement under fitness
91
00:06:35,260 --> 00:06:39,220
for purpose is you've got to
satisfy fitness for purpose,
92
00:06:39,220 --> 00:06:43,540
for whatever the purpose is.
So what you want to see is an
93
00:06:43,540 --> 00:06:47,590
express statement, a clear written
statement in your subcontract to
94
00:06:47,590 --> 00:06:51,880
clearly state that your design to
reasonable skill and care, and that
95
00:06:51,880 --> 00:06:56,920
then reduces the burden down to what
will probably fit within your pie.
96
00:06:56,920 --> 00:07:02,260
And what it does is it introduces a
requirement for somebody to prove
97
00:07:02,260 --> 00:07:05,470
that you've done something wrong,
that you've done something negligent,
98
00:07:05,470 --> 00:07:09,550
that you failed to use the reasonable
skill and care that is expected
99
00:07:09,550 --> 00:07:11,860
of a professional designer.
Then, also,
100
00:07:11,860 --> 00:07:15,670
unlike the fitness for purpose test,
even if something fails,
101
00:07:15,670 --> 00:07:19,630
if you're able to demonstrate that
you've done all of the things that a
102
00:07:19,630 --> 00:07:22,390
competent person would have done,
then you haven't done anything
103
00:07:22,390 --> 00:07:25,570
negligent and you therefore
can't be punished for it.
104
00:07:25,570 --> 00:07:29,470
So hopefully you can see there's a
huge disparity between those terms.
105
00:07:29,470 --> 00:07:32,020
On the one hand,
you've got the likelihood of being
106
00:07:32,020 --> 00:07:34,630
punished for things that you
haven't even thought about under
107
00:07:34,630 --> 00:07:37,600
the fitness for purpose argument.
And on the other hand,
108
00:07:37,600 --> 00:07:40,870
you're able to say, hold up,
it's not my fault, it's failed.
109
00:07:40,870 --> 00:07:44,740
I've done exactly what anybody else
would have done in my situation,
110
00:07:44,740 --> 00:07:48,160
and therefore it's the requirements
that must be wrong and not me.
111
00:07:48,280 --> 00:07:51,700
Now, hopefully that makes that clear.
Why you need to watch out for fitness
112
00:07:51,700 --> 00:07:55,450
for purpose statements within your
subcontract inquiries and within
113
00:07:55,450 --> 00:07:59,230
your subcontracts themselves.
And if you find them and hopefully
114
00:07:59,230 --> 00:08:02,950
you won't because contractors are
savvy to these statements as well.
115
00:08:02,950 --> 00:08:05,470
But that's not to say that
someone slipped through the net.
116
00:08:05,470 --> 00:08:08,890
If you find them, challenge them,
and don't be afraid to walk away
117
00:08:08,890 --> 00:08:12,370
from the work if you can't
negotiate those statements out.
118
00:08:12,370 --> 00:08:15,730
And if you didn't know this,
of course, the phrase reasonably
119
00:08:15,730 --> 00:08:18,400
fit for purpose probably
wouldn't raise any eyebrows.
120
00:08:18,400 --> 00:08:21,100
But now that you do,
you know what to do.
121
00:08:21,100 --> 00:08:24,550
Okay, well, next, I wanted to have
a look at the JCT subcontract.
122
00:08:24,550 --> 00:08:29,170
And if you look at the subcontractors
designed works clause, which is 2.2,
123
00:08:29,200 --> 00:08:34,060
this in typical JCT fashion, uses
far too many words to basically say
124
00:08:34,060 --> 00:08:38,470
design and specify the works you've
been asked to complete in accordance
125
00:08:38,470 --> 00:08:42,580
with the contractor's requirements
and your subcontractors proposals.
126
00:08:42,580 --> 00:08:45,940
It does also say, including any
work that you've been asked to
127
00:08:45,940 --> 00:08:49,450
complete as a result of a variation.
It then says you must comply
128
00:08:49,450 --> 00:08:53,170
with the contractor's directions
for integrating your design into
129
00:08:53,170 --> 00:08:56,410
the wider contract works and the
contract design, and then it
130
00:08:56,410 --> 00:09:01,450
refers you to clause 3.5.1.3,
which is an interesting clause that
131
00:09:01,450 --> 00:09:05,530
says that you must comply with what
the contractor requests you to whilst
132
00:09:05,530 --> 00:09:09,460
you're completing your design,
unless within five days you tell
133
00:09:09,460 --> 00:09:13,090
the contractor that that is either
going to compromise you completing
134
00:09:13,090 --> 00:09:17,080
the works under CDM, or compromise
the quality of your finished work
135
00:09:17,080 --> 00:09:20,800
or your ability to complete it.
And this is basically giving you some
136
00:09:20,800 --> 00:09:24,400
sort of means of kickback if the
contractor asks you to do something,
137
00:09:24,400 --> 00:09:27,520
but it's going to make it really
hard for you to complete your work,
138
00:09:27,520 --> 00:09:31,960
or it's going to result in something
illegal, i.e. non-compliant with CDM,
139
00:09:31,960 --> 00:09:35,620
then you basically have five
days to submit a notice to that
140
00:09:35,620 --> 00:09:38,860
effect and tell him about it.
Back to clause 2.2.
141
00:09:38,890 --> 00:09:42,220
It rounds up by reminding you
that you have to act under the
142
00:09:42,220 --> 00:09:46,270
CDM regulations,
and specifically clauses 8 to 10.
143
00:09:46,270 --> 00:09:49,360
I'll let you look those up on
your own time as they don't make
144
00:09:49,360 --> 00:09:52,030
exciting reading.
But these are the general duties,
145
00:09:52,030 --> 00:09:56,140
the duties of a designer and the
designs prepared or modified
146
00:09:56,140 --> 00:09:59,530
outside of Great Britain. Clauses.
Perhaps I'll come back to these
147
00:09:59,530 --> 00:10:01,720
and do an episode on them at
another time.
148
00:10:01,720 --> 00:10:05,920
Or if one of you puts me up to it.
And that concludes clause 2.2.
149
00:10:05,920 --> 00:10:08,770
Now if you thought that was far
too short and sweet, a whole
150
00:10:08,770 --> 00:10:14,440
further section 2.13 and 2.24 also
relates to the subcontract design.
151
00:10:14,440 --> 00:10:17,530
And then you have the design
submission procedure, which under the
152
00:10:17,530 --> 00:10:21,310
subcontract is schedule seven under
the main contract is schedule one,
153
00:10:21,310 --> 00:10:24,100
but they are a repeated version
of the same thing.
154
00:10:24,130 --> 00:10:27,700
The idea under the JCT suite of
contracts is that you support the
155
00:10:27,700 --> 00:10:31,870
contractor to submit their design
as a designing subcontractor,
156
00:10:31,870 --> 00:10:34,750
and of course, they've got their
architect, structural engineer
157
00:10:34,750 --> 00:10:37,870
and whatever other consultants
working directly for them.
158
00:10:37,870 --> 00:10:41,020
And the contractor has to coordinate
all of that design, or they can
159
00:10:41,020 --> 00:10:43,670
pass that design response.
Ability that coordination
160
00:10:43,670 --> 00:10:47,660
responsibility onto an architect,
say as the lead consultant,
161
00:10:47,660 --> 00:10:51,080
they are tasked with designing
everything and they may draw
162
00:10:51,080 --> 00:10:54,140
together the subcontract design,
the structural engineer,
163
00:10:54,140 --> 00:10:57,620
civil engineer and so on.
Make sure it's all coordinated
164
00:10:57,620 --> 00:11:01,250
and talks to each other.
In theory at least, they then make
165
00:11:01,250 --> 00:11:04,760
sure it ties up with the KPIs and
the employers requirements and
166
00:11:04,760 --> 00:11:08,630
present it to the employer to review.
The design submission procedure
167
00:11:08,630 --> 00:11:11,810
is quite straightforward.
There are some added complexities.
168
00:11:11,810 --> 00:11:15,590
If the project is using some
design management software,
169
00:11:15,590 --> 00:11:19,070
or a contract management software,
where sometimes designs are
170
00:11:19,070 --> 00:11:22,970
submitted to a portal and then
the administration of the design
171
00:11:22,970 --> 00:11:26,480
submission procedure is via that
portal as well, it doesn't really
172
00:11:26,480 --> 00:11:30,620
make it any more difficult on a
technical level, it's just that
173
00:11:30,620 --> 00:11:34,670
it's another technological barrier,
another system for you to get used to
174
00:11:34,670 --> 00:11:37,730
when you're submitting your design.
The principles, by and large,
175
00:11:37,730 --> 00:11:41,900
remain the same or very similar.
And it goes a little bit like this.
176
00:11:41,900 --> 00:11:45,860
The contractor submits his drawings
to the employer within 14 days
177
00:11:45,860 --> 00:11:49,700
of receipt of those drawings,
the contractor should receive a
178
00:11:49,700 --> 00:11:53,960
response from the employer with
a status either A, B, or C,
179
00:11:53,990 --> 00:11:58,340
and these statuses mean under A.
The document is perfect.
180
00:11:58,340 --> 00:12:02,300
The contractor can get on with
the work status, b the contractor
181
00:12:02,300 --> 00:12:05,210
can proceed with the document,
but there are some comments from
182
00:12:05,210 --> 00:12:09,530
the employer that need to be
incorporated and then status C the
183
00:12:09,530 --> 00:12:13,850
contractor can't proceed and must
resubmit the document for approval.
184
00:12:13,850 --> 00:12:17,900
So for A that's straightforward, you
just crack on and do the work with B.
185
00:12:17,900 --> 00:12:21,380
Presumably these are minor
points and minor tweaks.
186
00:12:21,380 --> 00:12:24,110
I like it,
but just change this a little bit.
187
00:12:24,110 --> 00:12:27,950
That might be used to select a color
or to slightly tweak a finish.
188
00:12:27,950 --> 00:12:31,910
And then status C this is
requiring whole resubmission.
189
00:12:31,910 --> 00:12:36,320
So for statuses B and C the design
can't be returned with a status
190
00:12:36,320 --> 00:12:39,380
B or C without any comments.
There can't just be a flat
191
00:12:39,380 --> 00:12:43,100
rejection with no reason behind it.
And sometimes that might be.
192
00:12:43,100 --> 00:12:46,610
We need to see your calculations
behind the design.
193
00:12:46,610 --> 00:12:49,760
Or it might be if you're proposing
something slightly different,
194
00:12:49,760 --> 00:12:52,190
they want to see how it works.
They want to understand the
195
00:12:52,190 --> 00:12:56,240
specification, how it compares to
what was in the contract originally.
196
00:12:56,240 --> 00:12:59,360
Or maybe the employer just
doesn't like it. Now.
197
00:12:59,360 --> 00:13:01,670
If the contractor doesn't agree
with the comments,
198
00:13:01,670 --> 00:13:05,000
they can notify the employer
within seven days of receiving the
199
00:13:05,000 --> 00:13:09,050
comments that they don't agree and
that they want an instruction.
200
00:13:09,050 --> 00:13:11,120
And that should give rise to a
change.
201
00:13:11,120 --> 00:13:14,030
Now, if the employer has just
rejected it because they don't like
202
00:13:14,030 --> 00:13:17,510
it and they've just given comments on
it, then this should give rise to a
203
00:13:17,510 --> 00:13:21,260
change, because the employer can't
just reject something that there's
204
00:13:21,260 --> 00:13:24,920
been designed and submitted and is
in accordance with the contract.
205
00:13:24,920 --> 00:13:29,270
But the employer, in my experience,
often misuses the process.
206
00:13:29,270 --> 00:13:32,390
And we'll start rejecting things
because they don't like it, because
207
00:13:32,390 --> 00:13:35,450
their preferences for something
slightly different, something else.
208
00:13:35,450 --> 00:13:38,960
I recall a situation where we had
a ceiling, which was in the main
209
00:13:38,960 --> 00:13:42,800
atrium of a building that we were
constructing, and we submitted a
210
00:13:42,800 --> 00:13:46,460
design which is near as dumb.
It reflected what was on the original
211
00:13:46,460 --> 00:13:50,030
architect's drawing, and the employer
decided they didn't like it.
212
00:13:50,030 --> 00:13:52,700
They started saying, hold on,
I think I'll be able to see my
213
00:13:52,700 --> 00:13:55,520
structural steel through this.
I want to be able to see this
214
00:13:55,520 --> 00:13:57,500
and nothing else.
I don't want to be able to look
215
00:13:57,500 --> 00:14:01,700
down the panels and start seeing
unsightly bits of the structure, and
216
00:14:01,700 --> 00:14:04,610
then started playing silly buggers
about what they actually wanted,
217
00:14:04,610 --> 00:14:08,150
saying, no, you're supposed to be
the designer. Make me a proposal.
218
00:14:08,150 --> 00:14:10,880
And well, our proposal,
which was in accordance with the
219
00:14:10,880 --> 00:14:14,420
contract they didn't like,
and we got given a real runaround
220
00:14:14,420 --> 00:14:17,300
and it ended up causing quite a
significant delay to this
221
00:14:17,300 --> 00:14:20,300
particular section, which was the
main entrance of the building.
222
00:14:20,300 --> 00:14:23,300
And actually, in hindsight,
we should have said, no way.
223
00:14:23,300 --> 00:14:26,420
Give us an instruction for what
you want if you don't want this,
224
00:14:26,420 --> 00:14:28,430
because this is exactly what
you've asked for.
225
00:14:28,430 --> 00:14:32,000
Or alternatively, we could have asked
the employer to demonstrate from
226
00:14:32,000 --> 00:14:35,750
the contract what specifically they
thought didn't comply with their
227
00:14:35,750 --> 00:14:39,140
requirements, and that should have
then drawn a line under the matter.
228
00:14:39,140 --> 00:14:42,260
Either we'd get on with that.
The employer, from my recollection,
229
00:14:42,260 --> 00:14:45,710
wouldn't have been able to justify
what they were saying, so we'd have
230
00:14:45,710 --> 00:14:48,950
just been able to carry on with
that design or resubmitted it,
231
00:14:48,950 --> 00:14:52,280
and it should have sailed through,
or they should have then stipulated
232
00:14:52,280 --> 00:14:56,090
what they wanted instead and give
us an instruction for that change.
233
00:14:56,090 --> 00:15:00,290
So if the contractor notifies the
employer that he would consider the
234
00:15:00,290 --> 00:15:03,950
comments to be a change, the employer
has then got seven days to come
235
00:15:03,950 --> 00:15:08,270
back to them and either restate or
confirm the comment or withdraw it.
236
00:15:08,270 --> 00:15:12,260
So if the comment is withdrawn, this
can change the document to status A.
237
00:15:12,260 --> 00:15:15,650
Otherwise the contractor has to
resubmit and this restarts the
238
00:15:15,650 --> 00:15:17,930
process.
So they have to incorporate the
239
00:15:17,930 --> 00:15:20,360
comments.
And the employers then got 14
240
00:15:20,360 --> 00:15:23,630
days to rereview everything.
Now that sounds reasonably
241
00:15:23,630 --> 00:15:26,210
straightforward.
So just to make it more interesting,
242
00:15:26,210 --> 00:15:29,060
the JCT adds in another couple
of items.
243
00:15:29,060 --> 00:15:33,110
So they state that confirmation or
withdrawal of a comment doesn't
244
00:15:33,110 --> 00:15:37,760
signify acceptance by the employer
that the relevant document or amended
245
00:15:37,760 --> 00:15:42,050
document is in accordance with the
contract, nor that compliance with.
246
00:15:42,160 --> 00:15:45,250
The employer's comment would
give rise to a change, so the
247
00:15:45,250 --> 00:15:48,550
employer can effectively insist
that the comment is incorporated
248
00:15:48,550 --> 00:15:51,550
without giving rise to a change.
So that means you need to fight
249
00:15:51,550 --> 00:15:54,370
your corner on that one.
The next comment says if the
250
00:15:54,370 --> 00:15:57,610
contractor doesn't notify the
employer that they think a comment
251
00:15:57,610 --> 00:16:01,150
gives rise to a change, then it
shall be treated as if it doesn't.
252
00:16:01,150 --> 00:16:05,470
So this is another strike while
the iron is hot issue or forever
253
00:16:05,470 --> 00:16:09,130
hold your peace.
And finally, neither compliance with
254
00:16:09,130 --> 00:16:12,970
the design submission procedure
in schedule one nor compliance
255
00:16:12,970 --> 00:16:16,000
with the employer's comments
shall diminish the contractor's
256
00:16:16,000 --> 00:16:20,410
obligations to ensure the contractors
design documents and works are in
257
00:16:20,410 --> 00:16:24,370
accordance with this contract.
And that means to say that even if
258
00:16:24,370 --> 00:16:28,150
the contractor has submitted the
design, the employer has given its
259
00:16:28,150 --> 00:16:32,110
status a crack on and build, and then
they later realize that something
260
00:16:32,110 --> 00:16:35,080
doesn't comply with the contract.
They can come back and pick on
261
00:16:35,080 --> 00:16:36,940
it later.
Sometimes that might mean that
262
00:16:36,940 --> 00:16:40,540
the employer has spotted some of
these things, but then decides to
263
00:16:40,540 --> 00:16:43,360
let you crack on and come back
for a saving at a later date.
264
00:16:43,360 --> 00:16:46,900
Sometimes it might mean that they
just haven't picked up on things.
265
00:16:46,900 --> 00:16:51,220
So say they've asked you to design
and construct a building to maintain
266
00:16:51,220 --> 00:16:54,910
a massive piece of plant which
is five metres tall, and during
267
00:16:54,910 --> 00:16:58,420
the design submission procedure,
you submit drawings for a hanger
268
00:16:58,420 --> 00:17:02,830
door which is only 4.7m tall.
If they don't pick up on that
269
00:17:02,830 --> 00:17:06,100
and they approve the drawing,
it goes to state to say they can
270
00:17:06,100 --> 00:17:09,730
still come back at a later time when
they can't get their five metre tall
271
00:17:09,730 --> 00:17:13,420
piece of plant through the door
and say, hold up, Mr. Contractor,
272
00:17:13,420 --> 00:17:16,690
you fucked this one up.
So it is in your best interest
273
00:17:16,690 --> 00:17:20,170
to comply with the employer's
requirements for that very reason.
274
00:17:20,200 --> 00:17:22,990
Now, just going back to those couple
of clauses that we missed out,
275
00:17:22,990 --> 00:17:26,260
the contractor will follow
largely the same process with you
276
00:17:26,260 --> 00:17:30,040
as their subcontract designer,
albeit they may water it down via
277
00:17:30,040 --> 00:17:33,700
amendments in their own conditions.
They may also lengthen your
278
00:17:33,700 --> 00:17:38,440
submission time scale explicitly,
so that they've got a period of
279
00:17:38,440 --> 00:17:41,650
time to review it themselves,
to pass that on to the client,
280
00:17:41,650 --> 00:17:45,280
and then for the client to do
their 14 day review, albeit it's
281
00:17:45,280 --> 00:17:49,090
not in the contractor's interest
in any way for them to delay you
282
00:17:49,090 --> 00:17:53,050
or for them to delay themselves by
delaying submitting your design.
283
00:17:53,050 --> 00:17:57,100
So they typically want to work to the
shortest timescale that they can.
284
00:17:57,400 --> 00:17:59,440
Of course,
when everything is finished, you
285
00:17:59,440 --> 00:18:02,830
have to provide as built drawings.
And this of course goes hand in
286
00:18:02,830 --> 00:18:06,280
hand with the health and safety
file and operation and
287
00:18:06,280 --> 00:18:09,910
maintenance manual file.
You are bound to provide a license
288
00:18:09,910 --> 00:18:14,560
for the contractor and the employer
to copy and use the subcontract
289
00:18:14,560 --> 00:18:18,670
design and reproduce any of it,
for the purpose of maintaining
290
00:18:18,670 --> 00:18:22,600
and extending the building.
They are not allowed to start using
291
00:18:22,600 --> 00:18:26,260
your design for purposes other
than that, and they can typically
292
00:18:26,260 --> 00:18:30,670
reassign that right onto a subsequent
purchaser of their building.
293
00:18:30,670 --> 00:18:33,850
And there is a statement to say
if the documents are used for
294
00:18:33,850 --> 00:18:37,000
any other purpose,
that you're not liable for that.
295
00:18:37,060 --> 00:18:40,840
And speaking of liability,
that brings us back nicely to 2.13,
296
00:18:40,840 --> 00:18:44,410
which we also mentioned earlier,
which is about design liability
297
00:18:44,410 --> 00:18:47,020
and limitation.
The intention of the subcontract
298
00:18:47,020 --> 00:18:51,130
is to create the same liability
as if you were an architect,
299
00:18:51,130 --> 00:18:55,240
designing specifically your section
of the building, your section of
300
00:18:55,240 --> 00:18:59,110
the overall contract design,
and so that you would have the
301
00:18:59,110 --> 00:19:03,460
same liability to the contractor
in terms of being an appropriate
302
00:19:03,460 --> 00:19:07,720
professional designer who is able to
complete that design adequately,
303
00:19:07,720 --> 00:19:11,890
and that you would carry the same
liability to the contractor as they
304
00:19:11,890 --> 00:19:15,700
carry upstream to their employer.
I think that about covers all of
305
00:19:15,700 --> 00:19:19,570
the meat on the bones when it comes
to design and build subcontract
306
00:19:19,570 --> 00:19:23,590
certainly the design aspect of them.
My mission with this show is to
307
00:19:23,590 --> 00:19:27,970
help the million SME subcontractors
working within the industry.
308
00:19:27,970 --> 00:19:31,300
If you've taken something away
of value from today's episode,
309
00:19:31,300 --> 00:19:34,270
I'd love it if you'd share the show
and pass on that value to somebody
310
00:19:34,270 --> 00:19:38,140
else who could benefit from hearing
it. And thanks for tuning in.
311
00:19:38,140 --> 00:19:41,140
As ever, if you like what you've
heard and you want to learn more,
312
00:19:41,140 --> 00:19:48,070
please do find us at WWE, NXT zone.
That's the letters Q, S, Dot zone,
313
00:19:48,070 --> 00:19:51,880
Zona where you can subscribe to
our training and support system
314
00:19:51,880 --> 00:19:55,030
for like minded subcontractors.
In there you'll find templates,
315
00:19:55,030 --> 00:19:58,720
how to videos, interviews, and more.
It's less than the price of a
316
00:19:58,720 --> 00:20:01,720
cup of coffee per day,
and you can cancel anytime.
317
00:20:01,810 --> 00:20:06,640
We're also on all your favorite
socials at SHS zone. Thanks again!
318
00:20:06,640 --> 00:20:09,430
I've been Jacob Austin and
you've been awesome!